Wrench Solutions – Project Management Information System

Applying Earned Value Management Successfully

When is Earned Value Management (EVM) applicable?

We say: in every single construction project.

We are not the only ones who think so. The Association for the Advancement of Cost Engineering (AACE), being more function and detail-oriented, addresses this at length in their Recommended Practices.

AACE defines two key concepts in Earned Value Management (EVM):

  1. Measurable work progress
  2. A focus on planning to establish the performance measurement baseline (PMB) against which performance will be tracked and evaluated.

Key benefits of Earned Value Management

Building blocks of Earned Value Management

  1. Define Work Breakdown Structure
  2. Identify Organizations
  3. Integrate Sub-systems
  4. Identify Overhead control
  5. Integrate Work breakdown structure and the Organization breakdown structure

What is Earned Value Management? and Why is it so useful as a measuring and monitoring tool?

Consider this example:

Scope of the project: This project comprises of laying a fence around a square plot of size 1 km on each side (A, B, C, D). Each side has a budget of 1000. The work is supposed to get over on the 4th week. The surveyor is conducting the survey to assess the progress after 4 weeks from the start date.

Side A, Side B, Side C are fully completed.

The Budgeted Cost of Work Scheduled BCWS(A), which is also known as the Planned Value (PV) for A = 1000$

Since ‘A’ got over, the Budgeted Cost of Work Performed BCWP (A), which is also known as Earned Value (EV) for ‘A’ = 1000$. The Actual cost (AC) incurred to complete side A = 1000$.

In the case of side ‘B’, PV=1000, AC=1000.

For Side ‘C’, PV=1000, EV=1000, AC=1000

And for Side ‘D’, PV=1000, EV=500, AC=800

Now let us consider the cumulative values for the project;

Planned Value (EV) = Budgeted Cost Of Work Scheduled (BCWS) = 4000

Earned Value (EV) = Budgeted Cost Of Work Performed (BCWP) = 3500

Actual Cost (AC) = Actual Cost Of Work Performed (ACWP) = 3800

Schedule Variance (SV) = EV-PV = 3500 – 4000 = -500

Schedule Variance % = (EV-PV) / PV *100 = -500 / 4000 *100 = -12.5%

Schedule Performance Index (SPI) = EV/PV = 3500 / 4000 = 0.875

Cost Variance (CV) = EV-AC = 3500 – 3800 = -300

Cost Performance Index (CPI) = EV / AC = 3500 / 3800 = 0.921

Estimate At Completion (EAC) = AC+( BAC – EV ) / CPI   = 3800 + (4000 – 3500) / 0.921 = 3800+542.8 = 4,342

Throughout the project if we can maintain a CPI and SPI which is greater than or equal to 1, then the project is doing well schedule wise and cost wise.” 

The ‘S’ Curve

The ‘S curve’ is widely used in project management to track the project. At regular intervals they plot the Planned Value (PV), Earned Value (EV) and the Actual Cost (AC) .

Conclusion 

Hope this gives a brief introduction about how EVM works. Of course, knowing this in theory is one thing, applying it is another. That’s why EVM is now part of the WRENCH philosophy and built into all our project management and monitoring solutions. In fact, based on customer feedback, we would go so far as to say that WRENCH is the only way for companies to successfully apply the principles of EVM in real life projects.

Read further

Bullet proofing earned value management

EVM Progress monitoring using ‘S’ curves and Histograms

Earned Value project management simplified

See you soon!

Exit mobile version