- Blog evm forecasting
- 02 Apr 2019
Applying Earned Value Management Successfully
When is Earned Value Management (EVM) applicable?
We say: in every single construction project.
We are not the only ones who think so. The Association for the Advancement of Cost Engineering (AACE), being more function and detail-oriented, addresses this at length in their Recommended Practices.
AACE defines two key concepts in Earned Value Management (EVM):
- Measurable work progress
- A focus on planning to establish the performance measurement baseline (PMB) against which performance will be tracked and evaluated.
Key benefits of Earned Value Management
- Earned value management is easy to understand.
- It simplifies project management. Just by focusing on a handful of ratios project stakeholders can check the health of their projects.
- It is scalable. Earned value management can be applied at a project level, program level and even at a portfolio level. It can be applied at multiple locations.
- The forecasting ability of the earned value management system helps project managers to be more proactive.
- Project managers can practice management by exceptions
- No more waiting for project status information – Earned value management systems supported by automated Project Management Information Systems can provide the status of the project at the press of a button.
Building blocks of Earned Value Management
- Define Work Breakdown Structure
- Identify Organizations
- Integrate Sub-systems
- Identify Overhead control
- Integrate Work breakdown structure and the Organization breakdown structure
What is Earned Value Management? and Why is it so useful as a measuring and monitoring tool?
Consider this example:
Scope of the project: This project comprises of laying a fence around a square plot of size 1 km on each side (A, B, C, D). Each side has a budget of 1000. The work is supposed to get over on the 4th week. The surveyor is conducting the survey to assess the progress after 4 weeks from the start date.
Side A, Side B, Side C are fully completed.
The Budgeted Cost of Work Scheduled BCWS(A), which is also known as the Planned Value (PV) for A = 1000$
Since ‘A’ got over, the Budgeted Cost of Work Performed BCWP (A), which is also known as Earned Value (EV) for ‘A’ = 1000$. The Actual cost (AC) incurred to complete side A = 1000$.
In the case of side ‘B’, PV=1000, AC=1000.
For Side ‘C’, PV=1000, EV=1000, AC=1000
And for Side ‘D’, PV=1000, EV=500, AC=800
Now let us consider the cumulative values for the project;
Planned Value (EV) = Budgeted Cost Of Work Scheduled (BCWS) = 4000
Earned Value (EV) = Budgeted Cost Of Work Performed (BCWP) = 3500
Actual Cost (AC) = Actual Cost Of Work Performed (ACWP) = 3800
Schedule Variance (SV) = EV-PV = 3500 – 4000 = -500
Schedule Variance % = (EV-PV) / PV *100 = -500 / 4000 *100 = -12.5%
Schedule Performance Index (SPI) = EV/PV = 3500 / 4000 = 0.875
Cost Variance (CV) = EV-AC = 3500 – 3800 = -300
Cost Performance Index (CPI) = EV / AC = 3500 / 3800 = 0.921
Estimate At Completion (EAC) = AC+( BAC – EV ) / CPI = 3800 + (4000 – 3500) / 0.921 = 3800+542.8 = 4,342
“Throughout the project if we can maintain a CPI and SPI which is greater than or equal to 1, then the project is doing well schedule wise and cost wise.”
The ‘S’ Curve
The ‘S curve’ is widely used in project management to track the project. At regular intervals they plot the Planned Value (PV), Earned Value (EV) and the Actual Cost (AC) .
- If SPI=1 and CPI=1, then all these curves would have intersected at PV.
- The Budget at Completion (BAC) is the sum of ‘PV’ of all the work from start of the project till the end.
- Based on these data, it is possible to forecast the Estimate at Completion (EAC)
- EAC = AC + (BAC-EV) / CPI (Assumption, the nature of the work is same)
Conclusion
- A Schedule Performance Index (SPI) =>1 indicates the project is doing well schedule wise
- A Schedule Performance Index (SPI) < 1, indicates that the project is lagging behind schedule wise
- If the Cost Performance Index (CPI) >=1, indicates that the work is getting completed within budget
- A Cost Performance Index (CPI) < 1 indicates that we have spent more than planned for the completed work.
Hope this gives a brief introduction about how EVM works. Of course, knowing this in theory is one thing, applying it is another. That’s why EVM is now part of the WRENCH philosophy and built into all our project management and monitoring solutions. In fact, based on customer feedback, we would go so far as to say that WRENCH is the only way for companies to successfully apply the principles of EVM in real life projects.
Read further
Bullet proofing earned value management
EVM Progress monitoring using ‘S’ curves and Histograms
Earned Value project management simplified
See you soon!
Expert in agile, predictive and hybrid project management. Researches on the application of Artificial Intelligence for better project outcomes. Works as a domain expert at Wrench Academy, the knowledge management division of Wrench Solutions, the makers of Smart Project Digital PMO.
Related Posts
Importance of Collaboration and Communication in Project Management in EPC Projects
As the EPC industry moves steadily towards digitisation and we’re seeing the emergence of an ever-increasing array of digital project management systems and Project Management Information systems (PMIS) in project management, it’s interesting to look…
- 21 Nov 2024
EPCM Systems in the Age of Digital Transformation
It’s become commonplace to hear statements about “The Benefits of Digital EPC software’ and ‘The Future of the Construction Industry’ and ‘Digital transformation in EPC sectors’, with some pundits dubbing the current era EPC 2.0…
- 14 Nov 2024
Archives
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- January 2024
- December 2023
- November 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- September 2020
- August 2020
- June 2020
- April 2020
- March 2020
- February 2020
- January 2020
- November 2019
- October 2019
- September 2019
- August 2019
- April 2019
- March 2019
- December 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- January 2018
- November 2017
- October 2017
- September 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017