- Project Management
- 10 Nov 2020
Project Management And Project Delays: The Imperfect Pair!
“Delays are inevitable and there’s nothing much I can do about it! “, retorted my Project Manager. It was a tough day that started off with a typical Client meeting. They insisted on contractor adherence to the approved baseline completion, playing deaf ears to any logical explanation. According to the latest schedule update, the project had slipped by over 6 months with all the mitigative measures rendered ineffective. As a part of the team, I can vouch there was no dearth in efforts, either from the project team or the management who wholeheartedly backed the PM. The question arises, how did it happen?
It is important to have an introspection of the existing system to identify deficiencies from within. They later become valuable inputs to the lessons learned register. A detailed register thus becomes an invaluable part of the organizational process assets.
Now the question, why do most projects end up with irrecoverable time delays and cost overruns? In an interesting data shared by McKinsey&Company in their work “The construction productivity imperative”, a whopping 98% of the projects were identified to have incurred budget overruns or delays! So, what are the root causes contributing to this abysmal performance?
There are a few which include delays, scope creep, variations, force majeure, differing site conditions et.al. The construction industry is reeling under the effects of COVID-19, as a result of which the prominence and importance of “Force Majeure” have increased multifold in recent months.
In this write-up, we’ll touch on the different types of delays and the importance of one of the most basic requirements often overlooked at the contractor level. The need for a well-defined communication plan!
The stakeholders are often caught in no man’s land without access to the right information at the right time. The project manager must ensure effective implementation of communication plan to bring all the stakeholders on a single page. In other words, to facilitate effective project management.
In projects where every discipline is a profit-making cost center, implementation of a communication plan becomes challenging. The stakeholders are more aligned to meet their functional targets, which may not benefit the project overall. The document flow suffers due to red tapism, inadvertently causing delays and much more! The process should be introspected at regular intervals to identify and weed out redundant phases. Another latent issue is bureaucracy. Bureaucracy and red-tapism together suffocate the project manager, depriving him of the information required to carry-the project forward. This results in the creation of adhoc haphazard plans, which will prove detrimental in the long run. No projects are ideal, but setting up an effective communication plan plays a key role in identifying and averting risks. Setting up an EDMS and a foolproof project controls and monitoring system is another way to implement effective project management measures. This helps the PM to be in a pro-active mode rather than a reactive one.
So are delays inevitable? From my experience, I’d have to concur with the project managers’ sentiment . Of the 15 projects I have been a part of over the past decade, just 1 project completed on schedule! A 7% success rate in this small sample set is not encouraging. There have even been instances with variations being issued on the date of contractual completion!
The secret here is how you make the most of delays and turn the tables around eventually reaping benefits. There are 4 types of delays generally seen in the industry
1. Excusable and Non-Compensable Delays
Delays caused by factors that are out of the owner/contractor realm. The contractor is entitled to time extensions without any cost compensation. Delays caused by COVID 19 , weather etc. are examples.
2. Excusable and Compensable Delays
These are the delays caused by the owner/employer and the contractor is eligible to claim for both; Time extensions and cost. Any change in design initiated by the owner/employer after the completion of subject works on site is an example for this scenario.
3. Inexcusable Delays
Contractor / subcontractor / vendors / suppliers are the delay contributors. The contractor is ineligible to claim any time extension or cost . Infact, the owner can exercise LAD (Liquidated Ascertained Damages) on the contractor if defined in the contract.
4. Concurrent Delays
Two delays occurring at the same time having an impact on the project critical path. The delay owners can either be the contractor or owner/ employer. Substantiation of such delays may require detailed analysis to make the gullible parties accountable.
The above forms the basis for commencing any delay analysis. There are myriad questions which the project management fraternity has been striving relentlessly to address.
“Time is Money”. Contractors often find themselves running short on both, staring into an abyss of irrecoverable losses!
Related Posts
Measuring ROI and Performance Metrics of PMIS Implementation
The adoption of PMIS systems has increased significantly in recent years as the trend of digitally transforming the EPC process continues to grow at a rapid pace. For such organisations, understanding how the features of…
- 17 Oct 2024
Potential Security Risks During a Project
We live in a digital age with technology affecting every aspect of industry and human life. The benefits of course are many, but at the same time it cannot be denied that – as with…
- 10 Oct 2024
Archives
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- January 2024
- December 2023
- November 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- September 2020
- August 2020
- June 2020
- April 2020
- March 2020
- February 2020
- January 2020
- November 2019
- October 2019
- September 2019
- August 2019
- April 2019
- March 2019
- December 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- January 2018
- November 2017
- October 2017
- September 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017