Why do construction projects fail? 2/3
Monitoring your project
In the first part, we explored the need for a holistic approach to project management, keeping in mind that projects are a mass of interconnected processes and people. This time, I’d like to talk about the importance of monitoring project progress, and why it matters so much in successful project delivery.
I believe the lack of effective monitoring, which is caused by the lack of accurate and reliable progress data, eventually is a huge factor in project failure/delay. Managers simply don’t have the information they need to do their jobs effectively.
What happens is that we monitor progress by comparing planned progress with so-called actual progress (so-called because we rely entirely on what is reported to us which is often unverified) and so don’t have a true picture of what’s going on. We’re measuring progress as we think it is – or as we think it should be – rather than as it actually is, in the real world. We’re going by subjective reports at best and guesstimates at worst.
Not only that, we’re using ‘old’ data – sometimes up to a month old. Companies do not have a way to capture work status as it happens i.e., in real time. Task completion dates are manually collected through phone calls, meetings, and even verbal reports. So, there is a lag in getting the data and also a lag in verifying it. And although we spend a great deal of thought and effort making a project plan that dove-tails milestones with activities and quality and so on, we have no way to carry it out! It’s like having a superb high-tech railway track with beautifully marked signposts and markers…but no train. Only people, walking along the track and trying hard to keep up with each other, and with the schedule. Result: If there’s a milestone coming up in 10 days, day 10 is usually when the manager realizes there’s something amiss. But is it really his fault? Is not the system set up for failure?
Of course, we do monitor projects. Dams, stadiums, bridges, power plants, highways – all monitored somehow or they wouldn’t be here today. But the problem is the word ‘somehow’. One could say projects are completed DESPITE the methods used to track and manage them, not because of them. And that is because projects are still managed manually. By human managers. By fallible human managers. And that is the crux: dependency on human effort is one of the biggest bottlenecks in project management.
In the last century, automation transformed the manufacturing industry by removing human inefficiencies from the manufacturing process. Why shouldn’t it do the same for construction? Fundamentally, construction is also a process. Not as linear as manufacturing, but a process nonetheless, and as such, likely to benefit from automation. Because automation is the only way to bridge the gap between theory and practice, between planned and actual.
I saw this play out in real life a few years ago when I was called in on a high-value fast-track project which had been on ice for a very long time. When it finally got the green light there was immense pressure to deliver quickly. I got involved through the design consultant who was my customer and after joint discussions with the contractor (who eventually became my customer also) we set up a model of automated monitoring that eliminated the need for human monitoring altogether. With this in place the work went ahead smoothly and the project was finished ahead of time, something that rarely happens in EPC.
Which proved to me that a system for accurate progress measurement is not just a cool high-tech addition to project infrastructure, it could be the difference between success and failure.
Have a question or insight about other factors that lead to project delay? Leave a comment.
Related Posts
How to Select a PMIS for Your Organisation
The modern Project Management Information System (PMIS) is a widely-tested and amply-proven product, having been used on global construction and engineering project management for a long time now. In EPC (Engineering, Procurement, and Construction) projects…
- 29 Nov 2024
Importance of Collaboration and Communication in Project Management in EPC Projects
As the EPC industry moves steadily towards digitisation and we’re seeing the emergence of an ever-increasing array of digital project management systems and Project Management Information systems (PMIS) in project management, it’s interesting to look…
- 21 Nov 2024
Archives
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- January 2024
- December 2023
- November 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- January 2022
- November 2021
- October 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- September 2020
- August 2020
- June 2020
- April 2020
- March 2020
- February 2020
- January 2020
- November 2019
- October 2019
- September 2019
- August 2019
- April 2019
- March 2019
- December 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- January 2018
- November 2017
- October 2017
- September 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017